Transportation Thursday Update is from Youngsville Mayor Ken Ritter to keep residents abreast of what is happening with road updates in Youngsville.
- Crest Circle – Asphalt complete. Cleaning/Punch list over the next week.
- Almonaster – Asphalt paving will be completed mid-next week.
- Marteau – Asphalt paving is to begin at the end of next week.
- Fieldcrest Subdivision – Patching begins in three weeks, with asphalt overlay to follow.
- 89/Fortune – Construction signage, utility location markings, etc. have begun. Clearing of trees along Le J’ardin d’bel are coming soon.